A private company is faced with the problem of setting up a cement plant. Which of the factors given below should be taken into consideration for this venture? (1) Abundant electricity (2) Abundant limestone/dolomite (3) Abundant labour force (4) Abundant gas (5) Accessibility to transportation (6) Abundant coal Choose the correct answer from the codes given below:

Show the answer and explanation

Answer: (c) 1, 2 and 5 only

Limestone, electricity and transport (a heavy, bulky product) decide the site.

Why the others are wrong

(a) Cement is not labour-intensive.

(b) Gas is not essential.

(d) Leaves out limestone.

The trap

Coal is used in kilns, but it can be transported — limestone decides the site.

🔒 Cement: raw-material oriented (limestone). Leading State: Rajasthan (limestone) / AP.